Dangote Extension Project

 

Client: Dangote Cement Plc 

Contractor : AUSTROPLAN Austrian Engineering GmbH, Austria

Date : 2013 – 2015

Description:   

Dangote Cement Plc, the CLIENT, has entered into an EPC Contract for the turn key execution of two new cement production line with a clinker capacity of 5,000 tonnes/day each in order to meet the growing demand of the customers inside and outside Ethiopia.

The CLIENT has entrusted Implementation Monitoring Consultant AUSTROPLAN Austrian Engineering GmbH, Vienna, Austria, to provide project monitoring and inspection of quality of work services at site and off shore inspection of Materials for the expansion of the Project consisting of Clinker Unit at Mugher, in Ethiopia. 

Europroiect Design, Austroplan’s subcontractor performed the followings works on site: Planning & Project Monitoring, Quality Work Inspection and Civil Engineering Monitoring.

Investment :  580 000 000 USD